Updated Thurs 19th July.....Updated Thurs 19th July

 The BIG Ampertaine Makeover!

Look What We've Achieved!!

 

Our hardworking PTA is planning to fulfil its commitment to completion of the list of requests from children and teachers drawn up in the spring.

For organisational reasons and to make it easier for volunteers to commit their time, three sessions have been arranged.

Tasks are designated as follows:

BLACK: Still to be allocated    GREEN: Team organised  Orange: Completed

We hope we can assume that teams will measure-up and bring materials to the site.
All receipts / invoices to be retained.

You can let us know of your energy levels and availability by contacting Garry in school at Summer Learning (Tuesdays / Thursdays) OR gmcilwaine565@c2kni.net OR any parent you know to be involved in our PTA... Victoria Shiels, Alison Linton, Sharon Hall, John Lynd,Heather Millar, Heather McDonald, Stephanie Sufferin OR Neil at the Linen Café.

A planning meeting will be organised beforehand.

Session 1

Friday 27th 6.30 pm-9.00 pm

Power hose front rendered wall on Kilrea Road
John Lynd & Team

Tyre Dome Session 1

Supply 26 x "safe" uniform car tyres + 4 "safe" slightly larger tyres   John Lynd
Installation of base levels of tyres
Robin Bolton & Team 

Room 2:
Paint ceiling 
Prepare walls / doors / architraves
Undercoat doors / architraves (6 volunteers)
Victoria Shiels, Alison Linton, 

 

Billy's Yard (Outdoor Play Area):
Erect safety fence at car park
Ian Millar & Team

This will take place during the second week of August. 

 

 

 

All black text shows tasks where help is needed, please.

 

Session 2.

Saturday 28th 10.00 am-2.00 pm

Room 2:
Paint walls

Billy's Yard (Outdoor Play Area):

Erect safety fence at car park
Ian Millar & Team

Mud play zone:
Installation of "sink unit"
Install Blue PVC piping and tap
Nigel Gibson + 1

Tyre Dome Session 2:
 Complete assembly to form play dome.  

Planters:
Supply & position 2 x "safe" tractors tyres and transfer existing planter materials


Ampertaine Villa Play House:
Replace damaged wood to floor and porch
Touch up paint
(4 Volunteers)
Gordon Linton + 3 more please 

 

 

All black text shows tasks where help is needed, please.

Session 3

Saturday 28th  2.00 pm - 6.00 pm

Room 2:

Paint doors / architraves 
Varnish wood panelling

Paint front wall:
Garry McIlwaine & Team

All black text shows tasks where help is needed, please.

Session 4

Week beginning 30th, exact time to be arranged....

Topping and Tailing
Lynda Pattison + jenny Sufferin  few more, please.

 

All black text shows tasks where help is needed, please.